SERVICE ANNOUNCEMENTS

13 August 2019

Early Closure and Late Opening of North-South Line Stations in August and September 2019

Singapore, 13 August 2019

Early Closure and Late Opening of North-South Line Stations in August and September 2019

  1. To facilitate power supply system renewal and maintenance works along the North-South Line, SMRT will extend engineering hours with early closures and late openings of selected stations in August and September 2019.
     
  2. From 24 August to 1 September 2019, six stations between Bukit Batok and Marsiling will open later at about 8.00am on Saturdays and Sundays. From 6 to 28 September 2019, four stations between Bukit Batok and Yew Tee will close earlier at about 11.00pm on selected Fridays and Saturdays. The additional engineering hours will be used to carry out viaduct bearing replacement works and installation of 22kV cables as part of the power supply system renewal works. 

Late Opening of Selected NSL MRT Stations
 

Period

Dates

Stations Affected

24 Aug –

1 Sep 2019

Saturday and Sunday:

24, 25, 31 Aug,

1 Sep

Late Opening at about 8.00am for six NSL MRT stations from Bukit Batok to Marsiling


Early Closure of Selected NSL MRT Stations

 

Period

 

Dates

 

Stations Affected

6 to 28 Sep 2019

 

 

Friday and Saturday:

6, 7, 13, 14, 27, 28 Sep

Early Closure at about 11.00pm for four NSL MRT stations from Bukit Batok to Yew Tee

 

Alternative Travel Arrangements

3. During these early closures and late openings, Shuttle Bus Service 4 will be available to maintain connectivity for commuters. The buses will stop at designated bus stops near the affected MRT stations to pick up and drop off passengers.
 

Dates

Shuttle Number

Service Area

Service Interval

Late Opening on 24, 25, 31 Aug and

1 Sep

4

Between Jurong East and Woodlands (Both directions)

3 – 5 minutes

Early Closure on 6, 7, 13, 14, 27 and 28 Sep

 

4

Between Jurong East and Kranji (Both directions)

3 – 5 minutes

Commuters Advised to Plan Ahead

4. The timing of the last trains' departure from each station during the planned closures will vary. Commuters are advised to check the departure times at affected MRT stations, or on SMRT Trains’ website and social media platforms, in order to plan their journeys ahead of time. More time may also be needed to travel between MRT stations using the shuttle bus services.
 

5. SMRT will keep commuters updated on changes in train operation hours and alternative transport arrangements on SMRT’s Trains’ website, https://www.smrttrains.com.sg, as well as through SMRT’s Facebook, Twitter feed and the SMRTConnect app.

-end-

Please see below for the posters: