New Signalling System To be Trialled During East-West Line Service Hours on Sundays from 29 April to End May 2018

Singapore, 24 April 2018

New Signalling System to be Trialled During East-West Line Service Hours on Sundays From 29 April to End May 2018

1. The Land Transport Authority (LTA) and SMRT will conduct trials of the new Communications-Based Train Control (CBTC) signalling system during East-West Line (EWL) passenger service hours on five Sundays from 29 April 2018 to 27 May 2018. 

2. With train services on the entire EWL operating on the new CBTC signalling system, services between Gul Circle and Joo Koon stations will also resume on the five Sundays from 29 April to 27 May 2018. The existing shuttle bus service connecting Gul Circle and Joo Koon will not operate on these dates.

3. These trials are part of the planned early closures and late openings of the North-South and East-West Lines (NSEWL) which started since December 2017 and have given LTA, SMRT and signalling system supplier Thales more time to implement the new signalling system on the EWL. Off-service trials have also been ongoing since February 2018 to fine-tune system performance. This includes ensuring accurate train-to-platform door alignment at EWL stations, smooth acceleration and deceleration of trains along EWL tunnels and viaducts, as well as the interface with North-South Line (NSL) operations. 

4. The latest version of the CBTC signalling software is also undergoing testing at the newly opened CBTC Signalling Simulation Facility in Bishan Depot. This facility will augment ongoing trials by simulating the reliability and robustness of the new signalling system under different test scenarios. These simulations can be done without impacting actual train services, and are tailored to the environmental and infrastructural conditions of the rail network in Singapore. Please refer to the Annex for examples of the simulations carried out in the facility.

5. Said LTA’s Deputy Chief Executive for Infrastructure and Development, Mr Chua Chong Kheng: “Together with SMRT and Thales, we have been conducting extensive testing of the new CBTC signalling system during off-service hours. Only after we were satisfied with its performance did we decide to commence trials during service hours, starting with five Sundays from end-April to end-May 2018. Trials conducted during service hours are important, as they give us an opportunity to expeditiously identify and resolve issues that may only surface when the system is operating under real-world operational loads.” 

6. Mr Chung Swee Hiang, SMRT Trains’ Chief Engineer for Signalling and Communications Maintenance, said: “The system’s performance in a live operating environment will be closely monitored over the next few Sundays. Our engineering team will work closely with the operations team to quickly rectify any new faults which we may not have encountered during off-service trials, and make adjustments according to operational needs. We ask for commuters’ patience and understanding, as we work with LTA and Thales to introduce the new signalling system for train service on the EWL gradually, with minimum inconvenience to commuters.”

7. The upcoming Sunday trials will not affect the EWL’s operating schedule. However, commuters may occasionally encounter instances of train and platform doors not opening or closing promptly, trains being held at stations longer than usual, or trains stopping momentarily between stations. LTA, SMRT and Thales will be deploying more staff and engineers on the ground to shorten the response time to any issues that may develop, and provide assistance to commuters.

8. LTA, SMRT and Thales are working to commence daily trials of the new CBTC signalling system on the EWL during the school holidays in late-May 2018.